This project installed a brand new kitchen in an underused addition built onto a 1902 bungalow.
New kitchen installation
This room was an addition
The wooden floor was removed to make way for tile
Concrete subfloor backing
Wood plank ceramic tiles were choosen
Detail of the wood plant ceramic tile
Detail of the grouted wood plant ceramic tile
The base cabinets went in
Full size pantry cabinet
Island detail
Wine cabinets with a wine cooler insert
Measuring for the marble countertop
4″ luan strips were glued together to form a countertop template
Countertop template over the sink
Countertop template over the island
Rough fitting the range exhaust fan
Cabinet shelf detail by the sink
Refrigerator cabinet
The wall cabinets were hung on the wall
Masking the refrigerator cabinet into the soffit
Crown moulding finish detail
Corner wall cabinet 45 degree
Crown moulding around the 45 degree cabinet
90 degree corner detail for the crown moulding
Wall cabinets crown moulding finish against the floor to ceiling pantry
Wall cabinets around the sink window
Marble countertops going in around the cooking range and stove
Marble countertop detail
Marble countertop underneath the 45 degree wall cabinet
The marble countertop was installed
Concrete backing for the tile backsplash behind the exhaust vent
Glass tiles being installed vertically from the top down
Top down installation of vertical tiles allows for a clean finish behind the stove
The masking tape on the vertical glass tiles keeps them from drifting
Finished glass tile backsplash with white grout
Exhaust hood being installed
Refrigerator being installed
A finished view from the kitchen island
Light fixtures and and vent were installed
Range and stove being installed
Finish view of the floor to ceiling pantry
Finished view underneath the 45 degree wall cabinet
Finished view through the sink window
Appliances were placed
The whole kitchen from start to finish took 6 weeks